US 101 Aux Lanes - SR 85 to Embarcadero Rd

Description: On US 101 from SR 85 ro Embarcadero Rd - Add auxiliary lanes in each direction

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Santa Clara
City Mountain View, Palo Alto
Zip Code 94043, 94303
 
Senate District
11
Assembly District 21
Congressional District 14
 
Caltrans District
04
 
 
County/State Route Santa Clara 101
Postmile Begin/End 49 52.2
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  3,203    3203  
Lane Miles Added (HOV)  8    0  
Peak Period Time Savings (minutes)  233,840    233840  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Santa Clara Valley Transportation Authority Gene Gonzalo (408) 952-4236   gene.gonzalo@vta.org
Design (PS&E) Phase
Santa Clara Valley Transportation Authority Gene Gonzalo (408) 952-4236   gene.gonzalo@vta.org
Right of Way Phase
Santa Clara Valley Transportation Authority Gene Gonzalo (408) 952-4236   gene.gonzalo@vta.org
Construction Phase
Caltrans Francis Mensah (510) 622-5946   francis_mensah@dot.ca.gov
 
Corridor System Management Plan
Caltrans Juliana Gum (510) 286-4579   juliana_gum@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
CMIA
$84,930 $-29,059 $55,871
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$17,328 $0 $17,328
Non Budgeted ETC
$0 $0 $0
 
Total**** $102,258 $-29,059 $73,199

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$3,534 $437 $3,971 $4,556
Design(PS&E)
$7,182 $998 $8,180 $8,569
Right of Way
$6,612 $-1,435 $5,177 $3,093
Construction
$84,930 $-29,059 $55,871 $53,268
 
Total* $102,258 $-29,059 $73,199 $69,486

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2007 

07/01/2009 
 

 
07/01/2007 

07/01/2009 
100  07/02/2007 

07/23/2009 


-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2009 

02/01/2011 
 

 
07/01/2009 

02/01/2011 
100  12/11/2008 

02/28/2011 


-1 
Begin Right of Way Phase

End Right of Way Phase
07/01/2009 

11/01/2010 
 

 
07/01/2009 

11/01/2010 
100  01/31/2009 

11/30/2010 


-1 
Begin Construction Phase

End Construction Phase
06/01/2011 

08/01/2013 
 

 
06/01/2011 

08/01/2013 
100  11/17/2011 

11/16/2015 
-6 

-28 
Begin Closeout Phase

End Closeout Phase
09/01/2013 

09/01/2014 
 

 
09/01/2013 

09/01/2014 
100  11/16/2015 

04/11/2018 
-27 

-44 
Corridor System Management Plan
Adoption Date 12/01/2009    12/01/2009  100  12/01/2010  -12 
Implementation Date 12/01/2009    12/01/2009  01/01/2011  -13 
????????
Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 3,203 3203
Lane Miles Added (HOV) 8 0
Peak Period Time Savings (minutes) 233,840 233840

Bond Funding Cost
Adopted:
$84,930,000
Current Approved:
$55,871,000
Actual Expenditures:
$53,328,000

 

Status as of December 31, 2023.